The vacuum extraction operation of the muffle furnace must strictly follow safety regulations and equipment requirements to ensure the smooth progress of experiments or production processes and avoid accidents. The following are detailed operational precautions:

1. Preparation before operation
Equipment inspection:
Vacuum system: Check whether the vacuum pump, vacuum valve, vacuum gauge and other components are intact, ensuring no air leakage, blockage or damage.
Sealing of furnace body: Check whether the sealing rings of the furnace door, observation window, flange interface and other parts are aging, deformed or damaged, and replace them with new ones if necessary.
Electrical system: Check if the power cords, heating elements, temperature controllers, and other electrical components are securely connected and free from short circuits or open circuits.
Environmental preparation:
Cleaning the furnace: Before vacuuming, thoroughly clean the furnace to remove impurities such as dust and oil, and avoid contaminating the vacuum environment.
Good ventilation: Ensure good ventilation in the operating environment and avoid the accumulation of oil vapor or other harmful gases in the vacuum pump.
Security protection:
Wear protective equipment: Operators should wear safety protective equipment such as goggles, gloves, and lab coats to avoid harm from high temperatures, high pressures, or chemical substances.
Prepare emergency equipment: Equip the operation site with emergency equipment such as fire extinguishers and first aid kits to respond to unexpected situations.

2. Vacuum pumping operation steps
Close the furnace door and lock it:
Ensure that the furnace door is tightly closed and the locking device is in place to avoid air leakage.
Start the vacuum pump:
Choose the appropriate vacuum pump: According to the vacuum requirements of the muffle furnace, choose the appropriate vacuum pump (such as mechanical pump, diffusion pump, etc.).
Open the bypass valve first, then the main valve: Before starting the vacuum pump, open the bypass valve first and let the vacuum pump run without load for a period of time to preheat and remove the gas inside the pump. Then gradually open the main valve and start vacuuming.
Observing changes in vacuum degree: During the vacuum pumping process, closely observe the reading of the vacuum gauge to ensure that the vacuum degree gradually increases and meets the process requirements.
Control the vacuum pumping speed:
Avoid vacuuming too quickly: Vacuuming too quickly may cause the materials inside the furnace to break or deform due to pressure differences. Therefore, the vacuum extraction speed should be controlled to gradually reduce the pressure inside the furnace.
Segmented vacuum pumping: For large or complex structured muffle furnaces, the segmented vacuum pumping method can be used, which means pumping to a lower vacuum degree first, maintaining it for a period of time, and then continuing to pump to a higher vacuum degree.
Operation after reaching the target vacuum degree:
Close the vacuum valve: When the vacuum degree reaches the process requirements, close the vacuum valve and stop vacuuming.
Maintain vacuum state: If it is necessary to maintain vacuum state for subsequent processing (such as heating, sintering, etc.), the vacuum degree should be checked regularly to ensure no air leakage.

3. Precautions during operation
Avoid vacuuming at high temperatures:
Preventing material oxidation or volatilization: Vacuuming at high temperatures may cause the material to react with residual gases in the furnace, leading to oxidation or volatilization. Therefore, vacuum pumping should be started only after the furnace temperature has dropped to a lower temperature.
Protecting the vacuum pump: High temperature gas entering the vacuum pump may damage its internal components or shorten its service life. Therefore, it is necessary to ensure that the temperature inside the furnace drops to a safe range before vacuuming.
Prevent vacuum pump oil backflow:
Use a check valve: Install a check valve between the vacuum pump and the muffle furnace to prevent the vacuum pump oil from being sucked back into the furnace when the pump is stopped.
Regularly replace vacuum pump oil: Vacuum pump oil will gradually contaminate and deteriorate during use, and new vacuum pump oil should be replaced regularly to ensure the normal operation of the vacuum pump.
Avoid severe vibrations or impacts:
Protecting equipment accuracy: Severe vibrations or impacts may damage the precision components of the muffle furnace (such as vacuum gauges, temperature controllers, etc.), affecting the accuracy and lifespan of the equipment. Therefore, during the operation, it is necessary to avoid applying severe vibrations or impacts to the equipment.
Pay attention to electrical safety:
Avoid short circuit or electric shock: When operating electrical components, ensure that the power supply is disconnected and use insulated tools for operation. Avoid operating electrical components in damp or flammable/explosive environments.

4. Post operation maintenance
Release the vacuum and open the furnace door:
Slowly release vacuum: After processing the sample, the vacuum inside the furnace should be slowly released to avoid damage to the furnace door or sample caused by the pressure difference.
Open the furnace door and ventilate: After releasing the vacuum, open the furnace door and ventilate for a period of time to eliminate residual gas and heat inside the furnace.
Cleaning the furnace and equipment:
Cleaning the furnace: Use a clean cloth or vacuum cleaner to remove dust and impurities from the furnace and keep it clean.
Cleaning the exterior of the equipment: Wipe the exterior of the equipment with a clean cloth to remove oil and dust, and keep the equipment clean.
Check and replace the sealing ring:
Check the condition of the sealing ring: Regularly inspect the condition of the sealing ring, and replace it promptly if aging, deformation, or damage is found.
Apply vacuum silicone grease: After replacing the new sealing ring, a thin layer of vacuum silicone grease can be applied to improve the sealing performance.
Record operational data and device status:
Record operation data: Record operation data such as vacuum pumping time, vacuum degree, temperature, etc. for subsequent analysis and improvement.
Record equipment status: Record the operating status, fault symptoms, and maintenance status of the equipment, providing a basis for equipment maintenance and upkeep.

prev:

next: the latest article

Contact Information

E-mail:
web@kejiafurnace.com
Address:
No.18 Hongye Road, Hi-tech zone , Zhengzhou, China, 450000
QQ tel Email WhatApp FaceBook

Tel Number

181-3719-5600

Email

web@kejiafurnace.com

WhatsApp

+86/18037178440

FaceBook

Zhengzhou/Kejia

kejialiuyan